Why are BCWP and BCWS null if the task is completed?



  • I'm having trouble with the Budgeted Cost of Work Performed (BCWP) and Budgeted Cost of Work Scheduled (BCWS). They both appear as null, even when the tasks are 100% complete!

    enter image description here



  • Ensure you've established a baseline and you have updated the Status Date. And check how the project is calculating EV. I believe you have two options: % complete or % physical complete. I don't think it will calculate properly using % work complete, which is what you're showing in the picture.