Can I link or have formulas between task times?



  • Is it possible to use a formula to get information from "TASK A" as an input "work" in task B?

    Example:

    Task A is fixed duration of 2 weeks. I have assigned some resources and the total work they do is 60 hours. Now.. Task B is fixed work. The fixed work has to be 100 hours(predefined number) - [Work done in Task A] = 40 hours.

    Cheers,



  • The Work field is not customizable. Furthermore, fields that are customizable with formulas such as Number1-30, Text1-30, etc. can only use values from the task itself, not other tasks.

    If there are only a few such tasks that need to be updated, do it manually. However, if there are many you'll need a macro to update one task based on another task. There are likely many ways to do this, what springs to mind is to tag these pairs of tasks with a code in a text field (such as Text1). The macro would loop through the tasks looking for a code that meets a pattern (e.g "Pair01_FixedWork") and then would search for its mate "Pair01_FixedDur" and update accordingly.

    Note: the macro would need to be run whenever the driving task information changes.