Task states besides "complete" and "incomplete" in TaskJuggler?



  • I am using TaskJuggler to manage a project. In my particular project, we are doing basic research, so some tasks are not guaranteed to be completed, due to large numbers of unknowns. I would like some way to denote that "we worked on this task, but this task is permanently incomplete because it is not complete-able".

    In my limited experience, TaskJuggler easily handles the task states of "incomplete" and "complete". Is there a way to denote other options outside of these two possibilities, such as a "failed" state?



  • Split your research tasks into two parts

    I am not familiar with TaskJuggler. However, I would recommend that you split your research tasks into two parts:

    1. Ascertain task feasibility.
    2. Work the task to completion.

    You can always complete the first task - the outcome would be either 'feasible' or 'not feasible'. The second one is a conditional task that kicks in only if the task is 'feasible'.