Total cost increases every week,



  • I am using the MS project,i have noticed that the total cost column of the project increases every time i enter actual work. i am not sure why is that! could it be because some of the ressources are not working on the planned task for that week. how to i prevent that?

    thank you !



  • Segregate all task in more small task resource wise, create more WBS and assign to resource name. Define hour based resource allocation. Create proper burn down chart for resources. Remember the basic , work,cost and time ratios. Calculate CPI = EV / AC SPI = EV / PV