S-Curve with % complete column on MS-Project



  • Does anyone have any idea or could provide me with any insight about how to setup S-Curve graph based on "% complete" column ? This would be very helpful as I am stuck with this task for 2 days.

    Thanks.



  • Under the tab [Report], you can select the [Burndown] report. This report shows the amount of open and completed tasks. You can also include the "% Complete" line in the graph. Example of a burndown graph


Log in to reply
 