MS project how to create alternative schedule to understand the impact of certain changes



  • We are using MS project professional.

    Question : Assume I have a schedule A. There are 4 developers assigned to A as well. My management asks if they pull 2 resources out what will happen to the schedule.

    1. Can I create an alternative schedule with 2 devs with existing tasks and constraints, estimates and compare with original schedule to understand the impact ? (Not a baseline)
    2. Can you use a revisioning in MS project. For example I go ahead and create new schedule with 2 devs and call it revision 2. Once I understand the impact can I revert back to original revision ?


  • Make a copy of the original schedule by doing Save As. Then change the number of resources, let it calculate and save the new schedule (Rev 2). Use the built-in Compare Projects feature to compare the two schedules (Report tab).